Restore London won the contract to remove the existing stone paved feature and surrounding brick paviours and completely renew with new materials.

The works comprised of fully detailed site surveys and various paved patterns options were provided.

New York stone & brick paviours were installed to exacting details and resulted in a stunning paved feature.


Key Facts

LOCATION

Henley on Thames

DURATION

6 Weeks

CLIENT

Norlands Via Invesco

COMPLETION DATE

May 2016

PRINCIPAL CONTRACTOR

Restore London

VALUE

£100K



“Restore London brought a level of quality craftsmanship and skill that is rare in today’s construction market. They worked collaboratively, bringing their wealth of knowledge to every detail. Their contribution to the National Portrait Gallery can be seen wherever you look in the project. ”


Jamie Fobert CBE