Royal Academy

Restore London undertook various elements of work to the listed fabric both internally and externally. The principal task was the careful removal of vaulted brick arches in the basement to allow for the construction of a new lift aperture.

Restore London also rebuilt a new concrete structure along with various restoration works to the timber and stonework in the gallery above as well as carrying out important roofing and structural works externally.


Key Facts

LOCATION

Piccadilly, London

DURATION

12 Weeks

CLIENT

The Royal Academy

COMPLETION DATE

Sept 2015

PRINCIPAL CONTRACTOR

CBRE

VALUE

£250K



“Restore London brought a level of quality craftsmanship and skill that is rare in today’s construction market. They worked collaboratively, bringing their wealth of knowledge to every detail. Their contribution to the National Portrait Gallery can be seen wherever you look in the project. ”


Jamie Fobert CBE

Architect, Jamie Fobert Architects